Company News Releases...
Pacific Booker Minerals Inc. Announces Power Availability
Vancouver BC, June 12, 2008
The Company is pleased to announce that it has confirmed the availability of power from the former Bell mine electrical facility located 22 km from the Morrison project site. The 138 kV service, which was extended to the Bell Mine in 1971, is now energized at 25 kV and can be re-energized to its design voltage. A new 24.7 km 138 kV overhead line will be constructed from the former Bell mine site to the proposed Morrison mine site substation. A transmission system Load Interconnection Study was also completed by BC Hydro for the proposed new load.
To view information regarding Pacific Booker Minerals Inc., please visit our
website home page and reports section at http://www.pacificbooker.com,
On Behalf of the Board of Directors
“Erik Tornquist”
Erik Tornquist, Director
|